MML Case Study- Safe Concordia Project

 

72 POB Installation Project

Client had a requirement to add 72 additional bunks to their vessel for a project in Brazil.

 

Key Project Dates:

 

Contract Award Date: 1st October 2010

Module Completion Date: 30th November 2010

(Ex Works, MML Suzhou)

Shipping times to Curacao: 5 Weeks

Modules arriving in Curacao (Dutch Antilles): 21st January 2011

Installation: 3 weeks (MML Installation Team)

Vessel Departure Date: 21st February 2011

 

Montage of installation of MML units on board the Safe Concordia.

All linking kits and tools are supplied by MML.

 

1. Barge bringing modules alongside.

2.1st unit brought on board for tie down to grillage Structure on deck.

3. As modules are placed on board, teams go in to perform the 'linking' of the units

4. Cover plates are removed from each module to allow the linking process inside

5.1st module on level 2 swinging into position

6. 7th unit loaded into position

 

MML has experienced installation engineers, that travel anywhere in the world to help oversee the hook-up & commissioning of the modules on board the vessels or platforms. Depending on the size of the project, this can take anything from a few days to several weeks.

7. Stairwells fitted to both ends of the accommodation block

9. 9th and final unit in position